1. Install boxes, conduit and wire for telephone and computer requirements.
  1. Install a basic fire alarm and security system to include door switches, motion detectors, smoke detectors and keypad with communication to village offices.



SITE REQUIREMENTS


The following information identifies some of the basic requirements for the site work.  The intent is to develop the existing site to integrate the Powerhouse with the existing and planned park uses.


1. Utilities

  1. Electric – Presently an overhead electrical service exists to the building from a pole located on Liberty Street with the meter located near the main entrance of the building.  For aesthetic purposes the service could be run underground with the meter located in a less visible area.
  1. Natural Gas – Michcon provided natural gas service from Liberty Street.
  2. Water & Sewer – Village water & sewer service would be run from Liberty Street mains.  A trash pump would have to be installed adjacent to the building due to elevation restrictions.
  3. Telephone – Install an underground conduit from the existing telephone pole on Liberty Street to building basement for telephone and cable services.


2. Barrier Free Access to Main Level

  1. Option 1 – Demo existing walk and stairs and construct a concrete ramp and stairs at the main entrance to the building to meet ADA requirements.
  1. Option 2 – Construct a wooden ramp and stairs to the main entrance to the building to meet ADA requirements.  This option would cost less and more closely follow the Secretary of the Interior's Standards by not damaging or diminishing the original construction.


3. Parking, Sidewalk & Landscape

  1. Pave existing parking area to the east of the building and install a new sidewalk to the main entrance of the building.
  1. Install sidewalk and stairs on the east side of the building to allow access from the main entrance to the creek on the south side of the building with a walkway along the creek.
  2. Install a pedestrian bridge across the spillway and sidewalk connecting the powerhouse to the ballpark pathway.
  3. Install site lighting for parking area and sidewalks.
  4. Restore landscaping damaged by site work activities.


4. Spillway Access Barrier

  1. Option 1 – Construct a small masonry or concrete seat wall with landscaping shrubs along both sides of the spillway to deter access to the spillway.
  1. Option 2 – Install a decorative wrought iron or other type of fence along both sides of the spillway.  This option would cost less and be less disruptive





5.  Donor Recognition

  1. Develop and construct an area to recognize the many people and organizations that contributed to the renovation project.  This could be signage, brick pavers or other means of identification.



FLUME & SPILLWAY REQUIREMENTS



The southeast section of Moore Lake relies on the Powerhouse flume to maintain a flow of water through the lake.  Without this flow the section of lake would become stagnant and fill with algae.


Whether the Powerhouse is utilized for power generation or not, the existing intake structure, piping and valves should be maintained to accommodate this flow of water.


With the continuing development and paving of natural areas, the amount of surface water runoff into Pettibone Creek is much greater and increases the potential for flooding.  Having the existing flume and equipment in good operating condition would provide the ability to control the excess water during flood conditions and relieve the pressure on the other dams and structures on Pettibone Creek.


In the Pettibone Creek Dam #1, National Dam Safety Program Inspection Report, prepared by Wade Trim Associates for the Village of Milford, Dated August 1998, one alternative that was mentioned was to utilize the existing flume during high water conditions to divert water around the dam.


Based on the design drawings, the flume is constructed of ½” thick welded steel pipe installed in 40 foot sections.  It is supported by concrete saddles every 12 feet and 12” diameter, 20 feet long, concrete piles in the marsh area south of Moore Lake and across the upper mill pond.  There are six concrete anchors and five expansion joints to allow for thermal expansion.  There is a 36” vertical vent pipe connected to the flume at the midway point which is now located in the parking lot of Rite Aid.  There is also an 8” pipe connection and valve pit just north of Commerce Street for a mill water supply to the manufacturing building.


The Village of Milford has inspected the flume by video camera and found it to be in good condition.  The only problem identified was the accumulation of sediment at the lower end of the flume.


The following is a summary of the recommended work associated with the flume and spillway:


1. Intake Trash Rack Replacement

  1. The existing trash rack is severely corroded and broken in the middle and should be replaced to prevent debris from being carried into the flume.




2. Concrete Repair at Intake, Spillway and Powerhouse

  1. The existing concrete structures are structurally sound but are in need of surface repairs due to spauling.


3. Handrail Repairs

  1. The existing handrails at the intake structure, spillway and Powerhouse are in need of repair.  The badly corroded or damaged areas should be replaced and the remaining sections should be prepped and painted.


4. Intake Valve Repair and Maintenance

  1. The intake valve is still operable but should be cleaned, painted and lubricated to keep it in good operating condition.


5. Flume Sediment Removal

  1. The sediment that has accumulated over the years at the lower end of the flume should be cleaned out to prevent plugging and allow for additional water flow.


6. Gate Valves and Flange Installation

  1. The original gate valves at the Powerhouse have all been removed or vandalized.  The valves should be replaced or at a minimum the openings need to be sealed to prevent water from entering the basement.
  1. The openings cut into the piping at the Powerhouse for inspection purposes should be sealed to prevent water from entering the basement.  These could be sealed with a clear covering to allow viewing of the water flowing through the pipes.
  2. The openings at the turbines should also be sealed for the same reason.


7. Piping and Tank Prep and Insulation

  1. Once the insulation is removed from the piping and tank within the building and the surfaces are prepped, they will need to be reinsulated.  This is required to prevent condensation and future corrosion.



POWER GENERATION REQUIREMENTS



Since the goal of the Powerhouse Restoration Committee is to preserve the building, and the flow of water through the flume should continue to maintain the quality of Moore Lake, it makes sense to explore the feasibility of utilizing the infrastructure and water flow to generate electricity.


The process in which to activate a power generating facility is a complicated one and requires the approval of several governing bodies; including the Federal Energy Regulatory Commission (FERC).  This report will present the general requirements of this process along with specific items of work.


Originally, the station contained two vertical, Francis type turbines, one 75 KW and one 62.5 KW capacity, manufactured by the James Leffel Company.  A Francis turbine is typically defined a having a runner with fixed vanes, to which the water enters the turbine in a radial direction, with respect to the shaft, and is discharged in an axial direction.  Principal components consist of the runner, a water supply case to convey the water to the runner, wicket gates to control the quantity of water and distribute it equally to the runner, and a draft tube to convey the water away from the turbine.


Both of the original turbine runners, shaft and wicket gates have been removed. However, the water supply case, and draft tube are still intact.  The mechanical energy derived from the turbines was converted to electrical energy through two generators located on the main level, which have also been removed, therefore requiring replacement.  For the purposes of this investigation, only one of the turbines would be replaced with original type equipment and the generator would be installed on the lower level to allow for other uses of the main floor.



Estimation of Potential Power Generation


As previously mentioned, the amount of power that can be generated by a hydroelectric plant is determined by the total head pressure or elevation of the water and the available water flow.  Since the head pressure remains relatively constant, the determining factor is the flow of water.


In order to accurately estimate the power generation capacity of the existing hydroelectric station, an analysis must be performed involving the hydrological and mechanical features of the site, along with the expected operation mode.


Originally, the hydroelectric station was operated as a “reservoir plant”.  In this situation the upstream reservoir capacity is used to augment the flow to the turbines, during periods of low stream flow.  This type of operation is typified by a reservoir whose water surface elevation is extremely variable, being lowered as additional flow is required, and raised during periods of excess stream flow.  While this type of system was acceptable at the time of construction, to operate the station as a reservoir plant today would be unacceptable due to the environmental considerations and numerous upstream residents who rely on a fairly constant stream level.


An alternative to the “reservoir plant” is the “run-of-river plant”.  In this mode of operation, the electrical generation is controlled solely by the available flow as it occurs, and therefore, the natural level of the upstream reservoir is unaffected.  This type of system would be acceptable for the Pettibone Plant.  


Since the flow of Pettibone Creek is essentially split for 3400 feet between the Powerhouse flume and the creek supplying the mill ponds, it will be assumed that half of the total flow would be available in each branch.


If the smaller of the original two generating units were operating at full load, the required water flow can be determined by the following formula:


Electrical Power (KW) = Q x H x Ep

             11.8


Where: Q = Flow of water (cfs)

  H = Available head (feet) 50 for the Pettibone Station

  Ep = Plant efficiency assumed to be 86%*

  11.8 = Conversion constant


* Based upon recommended values from “Feasibility Studies for Small Scale Hydropower Additions” – a guide manual, U. S. Army Corps of Engineers.


62.5 KW = Q x 50 x .86

  11.8


Flow Required for Rated Output, Q = 17.15 cfs



Vertical Francis type turbines can only be operated within a certain percent of their design flow.  At flows below this level, the turbines are unable to provide the required rotational speed, and at flows greater than this level, the turbine will begin to operate in a “run-a-way” mode and must be braked.  The lower and upper operating limits of a vertical Francis turbine, operating at design head, are approximately 50% and 100% of design flow respectively.



Therefore, the minimum flow required to operated the turbine would be:


Q (minimum) = Q (rated) x .5 = 8.6 cfs


From the State of Michigan, Department of Natural Resources, Fisheries Division, Special Report, titled Huron River Assessment, April 1995, Table 14, Pettibone Creek is identified as having a Median daily discharge of 22 cfs (cubic feet per second).  If half of this median daily discharge were allowed to flow through the turbine, then the median electric power output would be:


Median Electrical Power Generated (KW) = Q x H x Ep  

             11.8

  = (22 x ½) x 50 x .86  

11.8

  = 40.08 KW

             

If the power generated was used to supplement the power consumed at the Village well house and iron removal plant, located in Central Park, then the daily median cost savings could be calculated as:


Median Daily Cost Savings = 40 KW x 24 hours/Day x .0853 $/KWH *

    = $81.88 / Day


*Current energy charge for Municipal Water Pumping at 195 N. Main St.


It should be noted that this is only an estimate of the average cost savings and the actual amount would depend on the seasonal rainfall and resulting flow of water in Pettibone Creek, as well as the length of time the turbine/generator was on line.


If the turbine and generator were operating at rated capacity for one day, the cost savings would be:


Maximum Daily Cost Savings = 62.5 KW x 24 hours/Day x .0853 $/KWH

       = $134.09 / Day


Continue                         Back to Powerhouse Project Page                                Home

Powerhouse Restoration Proposal Continued